OBJECTIVES

Roux was retained to reduce the projected time to complete groundwater remediation at this Superfund site. Roux successfully optimized operation of the existing system, installed a phytoremediation plot, and added an In Situ Chemical Reduction (ISCR) program. Projected time to complete remediation was reduced from eighteen to five years with cost savings of $9 million.

Click here to learn more about our Industrial Services.

PROJECT DETAILS
Location

New Jersey

Client

PRP Group

Roux Services

System Operation Optimization

Phytoremediation Plot Installation

In Situ Chemical Reduction (ISCR) Program